Maintenance and repair of municipal depot in Vredenburg, including external wall painting. Compulsory meeting on 06 October 2026 at 10h00. Completion within 4 working weeks after official order. Penalty of R500 per day for late completion. 2-year guarantee on workmanship and materials. 80/20 preference point system. B-BBEE certificate and locality proof required. CIDB registration 1GB required. Health and safety file required within 1 week of order. Contract value up to R300,000.
The works must be completed within 4 working weeks after receipt of an official order, as stated: saldanha bay municipality requires that the works be completed within 4four working weeks after receipt of an official order.
Payment is made only for satisfactorily completed work, minus retention money, per the schedule of rates and prices. The text states: payment will be made only for work satisfactory completed, minus retention money.
All workmanship and material are guaranteed for a minimum of 2 years from completion date. The text states: all workmanship and material shall be guaranteed for a minimum period of 2 years, from the date of completion of work.
The 80/20 preference point system applies, with points for price and specific goals. The text states: the **** system for requirements with a rand value of up to r50 000 000.
Minimum of two previously successfully completed projects of a similar nature within the past three years, with written references, invoices, or purchase orders as proof. The text states: minimum of two previously successfully completed projects of a similar nature completed within the past three years.
Penalty of R500 per day for late completion. The text states: he shall pay to saldanha bay municipality as penalties the amount of r500, 00 five hundred rand for each day or part thereof during which the works remain incomplete.
Inspection of the site is a condition of tender. The text states: it is a condition of tender that the tenderer shall have carried out a full and detailed inspection of the tender documents and shall have inspected the site if applicable.
Failure to submit compulsory documents or insufficient proof at closing time results in a score of zero. The text states: a score of 0 zero will be allocated if compulsory documents not duly completed and signed and if insufficient proof submitted at the closing time and date.
The contract will lapse with a value of R300,000. The text states: the contract will lapse with the contract value of r300 ****.