Supply, deliver and install 11kV switchgear and XLPE armoured underground cable at Pinetown substation. Compulsory briefing on 17 Nov 2026. Bids due 24 Nov 2026, 12:00. Requires CIDB 3EP or higher, qualified electrician, valid category C green certificate. Technical threshold 70%. Price 80%, specific goals 20%. 6-month duration. Penalties for delays.
Work must be completed within 6 months. The document states: the overall duration of the work shall not exceed six 6 months for actual work payment purposes.
Payment is made within 30 days of receipt of a correct tax invoice. The document states: prasa pays for the item within 30 days of receipt of the suppliers correct tax invoice.
The supplier warrants items are free from defects for one year. The document states: will remain free from defects for a period of one year unless another period is stated in the order from acceptance of the items by prasa.
Price is weighted 80 points and specific goals 20 points. The document states: price 80 specific goals 20 total points for price and specific goals 100.
Requires CIDB grading 3EP or higher and valid certificates. The document states: valid cidb grading of 3ep or higher and qualified electrician with trade test technician or engineer in electrical engineering.
Penalty of 0. 3% of contract price per delayed day, max 10%. The document states: an amount calculated 0. 3 of the contract price per delayed day. . . shall not exceed the maximum of 10 of the contract price.
Compulsory briefing and site meeting. The document states: compulsory tender briefing and site meeting on 17 November 2026 at 10h00.
Complaints can be lodged via email. The document states: bidders are advised utilize this email address ***@***. *. * for lodging of complains to prasa in relation to this bid process.
Failure to submit mandatory documents leads to disqualification. The document states: failure to provide mandatory returnable documents at the closing date and time of this rfq may result in a respondents disqualification.