This is an RFQ for the supply, delivery, and installation of a 0. 25ml steel pressure water tank at La Porte Vase Plots. Bidders must have a CIDB grading of 2ME or above. The closing date for submissions is 26 March 2026 at 12:00 noon. Bids must be submitted in original, sealed envelopes. Late submissions will not be accepted. The bid is subject to the 80/20 preferential points system. Bidders are required to submit 5 or more appointment letters and completion letters/certificates of similar work done, as well as a CV with certified copies of qualifications for the project manager. Proof of CSD registration is mandatory. Non-refundable printing fee of **** applies.
The bid must be submitted by no later than 12:00 noon on the closing date, which is 26 March 2026.
The bid notice states that payment will be made within 30 days after receipt of an invoice accompanied by the delivery note.
The bid notice mentions that the supplier warrants that the goods supplied are new, unused, of the most recent or current models, and that they incorporate all recent improvements in design and materials. This warranty remains valid for twelve 12 months after the goods have been delivered and accepted, or for eighteen 18 months after the date of shipment, whichever period concludes earlier, unless specified otherwise.
The bid notice states that RFQs will be evaluated according to the 80/20 preferential points system. The municipality does not bind itself to accepting the lowest bid or awarding a contract to the bidder scoring the highest number of points.
Bidders must have a CIDB grading of 2ME and above. They are also required to submit 5 or more appointment letters and completion letters/certificates of similar work done, and a CV with certified copies of qualifications for the project manager.
The bid notice indicates that if the supplier fails to deliver any or all of the goods or to perform the services within the periods specified in the contract, the purchaser shall, without prejudice to its other remedies under the contract, deduct from the contract price, as a penalty, a sum calculated on the delivered price of the delayed goods or unperformed services using the current prime interest rate calculated for each day of the delay until actual delivery or performance.
The bid notice mentions that site or information meetings, if specified, are compulsory. Bids will not be accepted from bidders who have not attended compulsory site or information meetings. However, no specific date or time for a site visit is mentioned in the provided text.
The bid notice states that samples, if requested, are to be provided to the municipality with the tender document.